Streets, pipes and buildings
At the end of FY2025 the city's roads, pipes, buildings, land and equipment were carried at $508.6M after depreciation. The capital improvement plan in the FY2027 proposed budget lists $301.6M of projects.
- Net book value, FY2025
- $508.6M
- Original cost remaining, FY2025
- 42.3%
- Depreciable assets of the city's governmental activities
- Capital plan, FY2027 proposed budget
- $301.6M
- Projects planned or under way, total estimated cost
Net book value by category, FY2025
Is the city keeping up?
Net book value against original cost is an accounting measure of age: it says how much of an asset's cost has been written off over its expected life, not what condition it is in. Only an engineering assessment can say that. The share of original cost remaining stayed within two percentage points of 43.7% in FY2018; it was 42.3% in FY2025. In FY2025 the city added $17.9M to these assets, against $11.4M of depreciation: 156.3% of the year's depreciation.
| Year | Depreciation | Added | Share of depreciation |
|---|---|---|---|
| FY2025 | $11.4M | $17.9M | 156% |
| FY2024 | $10.7M | $21.3M | 200% |
| FY2023 | $9.5M | $18.1M | 190% |
| FY2022 | $9.4M | $14.3M | 153% |
| FY2020 | $8.7M | $4.7M | 53% |
| FY2019 | $8.3M | $5.0M | 61% |
| FY2018 | $8.1M | $14.9M | 184% |
All capital assets of the city's governmental activities, depreciable or not: a project under construction is an addition to construction in progress. Years whose report records no depreciation are left out.
What is being built?
The capital improvement plan from the FY2027 proposed budget, by category: how many projects, their total estimated cost, the amount budgeted for the plan's year, and what has been spent on them so far. These are plans and estimates, not audited results. Follow individual projects on the project tracker.
| Category | Projects | Total estimate | This year's budget | Spent to date |
|---|---|---|---|---|
| Water | 22 | $173.8M | $62.5M | $25.6M |
| Facilities | 7 | $88.8M | $43.7M | $2.3M |
| Public Works | 13 | $31.9M | $14.2M | $5.2M |
| Parks | 2 | $7.0M | $3.3M | $1.0M |
Terms on this page
- Net book value of capital assets
- What the city's infrastructure, buildings, land and equipment are carried at on its books: their original cost less the depreciation recorded so far, for all of the city's activities.
- Capital improvement plan
- The total estimated cost of the projects in the city's capital improvement plan, planned or under way, across every fund that pays for them.
- Original cost remaining
- How much of the original cost of the city's depreciable assets has not yet been written off as depreciation. An accounting measure of age, not of condition.
- Added to capital assets
- What the city added to its capital assets in the year — depreciable assets and construction in progress alike.
- Depreciation
- The part of the cost of the city's depreciable assets written off in the year as they age.
- Reinvestment as a share of depreciation
- What the city added to its capital assets in the year, as a share of the year's depreciation. Above 100% means it added more than wore off on its books.
Where these numbers come from
Capital assets, FY2018: City of Petaluma ACFR FY2017–18, p. 88
Capital assets, FY2019: City of Petaluma ACFR FY2018–19, p. 93
Capital assets, FY2020: City of Petaluma ACFR FY2019–20, p. 94
Capital assets, FY2022: City of Petaluma ACFR FY2021–22, p. 95
Capital assets, FY2023: City of Petaluma ACFR FY2022–23, p. 95
Capital assets, FY2024: City of Petaluma ACFR FY2023–24, p. 95
Capital assets, FY2025: City of Petaluma ACFR FY2024–25, p. 95
Capital improvement plan, FY2027: FY2026–27 Proposed Operating & Capital Improvement Budget
Capital asset roll-forward: ACFR FY2024–25, Note 5, pp. 95–96 (FY2025); ACFR FY2023–24, Note 5, pp. 95–96 (FY2024); each earlier year from that year's own report. Capital improvement plan: the FY2026–27 Proposed Budget.